Испытания KNX-щитов: диэлектрическое испытание, УЗО и протокол по местным нормам

SmartMāja Engineering Team·2026-12-04·8 min read

Every KNX distribution board and main switchboard assembly must be tested and verified to IEC 61439-1/2 (Low-voltage switchgear and controlgear assemblies) before commissioning. This involves dielectric voltage withstand tests, RCD and RCBO trip testing, insulation resistance measurement, and loop impedance measurement — then documented in a commissioning sign-off certificate (BS 7671 Schedule of Test Results in the UK; PV3 or equivalent in continental Europe). This guide covers the test sequence, instruments, pass/fail criteria, and documentation.

IEC 61439 panel verification overview

IEC 61439-1 (General rules) and IEC 61439-2 (Power switchgear assemblies) define two verification types: (1) Design verification — type-tested by manufacturer (temperature rise, dielectric, short-circuit), not repeated at site. (2) Routine verification — required at site for each assembly: visual inspection, wiring check, dielectric test (spot check), electrical function test. For KNX panels: standard electrical verification applies to the 230V/400V distribution side — the KNX TP bus (29V DC SELV) is separately verified via ETS6 bus scan and telegram test. Routine verification is mandatory per IEC 61439-1 clause 11 and must be documented in the panel dossier (technical file).

Visual inspection and wiring check

Before any powered test: (1) Verify tightness of all bus bar connections (use calibrated torque screwdriver — typical M6 bolt = 6 Nm, M8 = 12 Nm, per manufacturer spec). (2) Verify cable conductor cross-sections match circuit breaker ratings and cable schedule. (3) Verify correct wire colours (L=brown/black/grey, N=blue, PE=green-yellow). (4) Verify RCD/RCBO connections (line to line terminal, load to load terminal — never reversed). (5) Verify KNX PS640 power supply connections (KNX+ red terminal, KNX− black terminal, PE earth). (6) Check DIN-rail spring clip engagement on all modules — no loose devices. (7) Verify all cable glands/knockouts sealed (IP protection of enclosure). (8) Verify busbar shield cover fitted on incomer. Record pass/fail per item in test sheet.

Dielectric voltage withstand test

IEC 61439-1 clause 11.9: routine dielectric test at 1000V AC (2× rated voltage + 1000V for assemblies ≤300V) or 1500V DC. Test instrument: portable hipot tester (e.g., Megger MIT400 with high-voltage output, or Fluke 1550C). Procedure: (1) Disconnect all sensitive electronics (KNX actuators, DIN-rail power supplies, SMPS — disconnect AC input to protect them from 1000V). Leave MCBs, RCDs, contactors connected. (2) Short all outgoing circuit conductors to PE. (3) Apply 1000V AC for 1 second between all live conductors (L+N) collectively and PE. Pass criterion: no breakdown (flashover), leakage current < 30mA. (4) For assemblies with sensitive electronics: apply only 500V DC spot test for 1 second instead — IEC 61439-1 allows reduced test voltage for assembled equipment. (5) Record: test voltage, duration, leakage current, pass/fail.

RCD and RCBO trip testing

Test instrument: RCD tester (Fluke 1660 installation tester, or Megger MFT1741). BS 7671 Table 41.1 (UK) / IEC 60364-4-41: maximum disconnection times for RCDs: 30mA RCD → must trip in ≤300ms at rated trip current (30mA). ≤0.5× rated current must NOT trip (no nuisance). Test sequence per RCD: (1) Half-current (15mA for 30mA RCD): apply, confirm NO trip for 300ms. (2) Rated current (30mA): apply, measure trip time, must be ≤300ms. (3) 5× rated current (150mA): must trip in ≤40ms. (4) Test button: press test button on RCD front, confirm trips. RCBO additional test: verify overcurrent protection — trip at 1.13× rated current (10-minute test) and 1.45× (within 1 hour) per IEC 60898-1. In practice, installers use the RCD tester automatic sequence which performs all steps. Record: RCD circuit reference, rated trip current, measured trip time at rated current, pass/fail.

Insulation resistance measurement

Test instrument: insulation resistance tester (Megger MIT400, Fluke 1587). Test voltage: 500V DC for 230V circuits per BS 7671 / IEC 60364-6. Minimum IR: ≥1 MΩ between all live conductors (L, N) connected together and earth. Procedure: (1) Switch off all MCBs/RCBOs (open circuit breakers disconnects loads). (2) Remove all plugs and loads from sockets. (3) Switch on all isolators. (4) Short L and N conductors of each circuit (via test short plug or bridging clip). (5) Apply 500V DC between L+N (shorted) and PE for 1 minute. (6) Read IR: must be ≥1 MΩ (good values: 100–500 MΩ for new installation, >2 MΩ minimum practice standard). (7) If < 1 MΩ: suspect damaged cable insulation, water ingress, or faulty load — isolate and retest in sections. Record per circuit: circuit reference, test voltage, measured IR in MΩ, pass/fail.

Loop impedance and prospective fault current

Test instrument: loop impedance tester (Fluke 1662, Megger MFT1741). Purpose: verify that the earth fault loop impedance (Zs) is low enough for the overcurrent protective device to disconnect within the required time (IEC 60364-4-41). BS 7671 Table 41.2: for B-type MCB 16A, maximum Zs = 2.87Ω (for 0.4s disconnection). Procedure (live test): apply loop tester between L and PE at furthest socket/load point of each circuit. Record measured Zs. Compare to maximum Zs for MCB type and rating from BS 7671 or equivalent. For KNX panels: test at the KNX actuator 230V input terminal (furthest load on the circuit). Prospective short-circuit current (PSCC): measured at incomer terminals with PFC tester — must not exceed panel SCPD (short-circuit protective device) rating (e.g., 10kA for typical DN63A incomer MCB). Record: circuit reference, measured Zs, maximum permitted Zs, PSCC at incomer, pass/fail.

KNX TP bus electrical verification

Separate from IEC 61439 testing: verify KNX TP bus integrity. (1) Bus voltage: measure KNX+ to KNX− at furthest device on each line — must be ≥22V DC (minimum, per KNX standard, nominal 29V). (2) Bus current: measure total current on PS640 output — must be within PS640 rated output (640mA). If over → add PS1280 or split line. (3) Polarity: verify KNX+ (red wire) and KNX− (black wire) not reversed at any junction (polarity reversal prevents bus power reaching devices beyond the reversal point). (4) ETS6 bus scan: in ETS6 > Topology > scan bus → all device individual addresses appear. Any missing device → check wiring fault at that device. (5) Test telegrams: ETS6 Group Monitor → send test telegrams to each actuator GA → verify response → all actuators respond. Document KNX TP test results alongside IEC 61439 electrical test certificate.

Нужна помощь с KNX- или DALI-проектом?

Сертифицированные инженеры SmartMāja помогут с проектированием щита, пусконаладкой, интеграциями и нестандартными сценариями. Первая консультация бесплатна.

Связаться с инженерами →

Ещё технические статьи

Loading...
Back to top